Nuevaunión - Applying Capital and Infrastructure Synergies to Support Development of the Relincho and La Fortuna Deposits
Additonal authors: Bergholz, W.. Book title: Proceedings of the 58th Conference of Metallurgists Hosting Copper 2019. Chapter: . Chapter title:
Proceedings, Vol. Proceedings of the 58th Conference of Metallurgists Hosting Copper 2019, 2019
Velásquez, C.
NuevaUnión SpA (NuevaUnión) is a development project located in the Huasco province of the Atacama region of Chile. It is held in a joint venture company owned 50:50 by Teck Resources Limited (Teck) and Newmont Goldcorp. It includes the Cu-Mo Relincho deposit and the Cu-Au La Fortuna deposit, with plans to utilise a single concentrator to be built at the Relincho site. The Relincho site is at an altitude of 2,000 masl and is 40 km from the La Fortuna site which is at an altitude of 4,100 masl. The project is currently completing a Feasibility Study and is reviewing equipment selection and flowsheet options. This paper is based on the current thinking, and design decisions will be finalized at the completion of the Feasibility Study. NuevaUnión is currently planning for phased operation, processing Relincho ore at 104 ktpd followed by processing ore from La Fortuna at 116 ktpd. Plans for the third phase include doubling the main processing lines and returning to Relincho ore at a processing rate of 208 ktpd. The NuevaUnión concentrator will incorporate comminution and flotation circuits that are being designed to maximize the overall economic value of the combined ore deposits. Major ore characteristics differ between the two ore bodies, such as ore competency, grindability, liberation grind size, pulp rheology, tailings properties, minerals and metals of value, as well as gangue mineralogy. Mineral processing choices have been made to optimise value from each deposit and the combined project.
INTRODUCTION
Between 2010 and 2013, two significant mining projects were being developed in Chile: Goldcorp’s El Morro project had recently finalized a Feasibility Study and, in 2011, had received its environmental approval for construction; and Teck Resources Limited’s (Teck) Relincho project was finalizing a Feasibility Study and preparing its Environmental Impact Study. Both projects were:
Geographically close, at only 40 km apart.
Considering similar infrastructure. Each was planning to have its own concentrator, tailings management facility, high voltage power line, port, concentrate transport system, seawater desalination plant and pumping system to mine site.
Keywords:
Copper 2019, COM2019